Most electronics projects do not fail in production. They fail at the prototype stage, when the design turns out to be impossible to build, or expensive, or both — and by the time that becomes clear, the tooling and the moulds have already been paid for.
Why we run prototypes on production lines
A prototype built on a separate bench line tells you very little. The paste stencil is different, the reflow profile is different, the placement tolerance is different, and the components may be hand-placed rather than machine-placed. The sample looks right, and then the production run behaves differently.
So we build prototypes on the production SMT lines, with the same 100% AOI inspection and the same functional test. What you validate is what you will receive. It is not a slower version of production — it is production, at low volume.
What 15 days actually covers
The 15-day figure is measured from receipt of build-ready files, not from the day you first emailed us. Inside that window:
- Engineering review — Gerbers, BOM and assembly drawings read before anything is booked, so assembly problems are found on paper rather than on the line.
- Material procurement — components sourced and incoming-verified against the part number.
- Build — placement, soldering, inspection.
- Test — functional test against your test plan, with the result recorded per unit.
- Dispatch — with the inspection report.
Material availability is the variable that decides most dates, not placement speed. A prototype with an obscure part on the BOM will wait for the part. That is why the engineering review flags long-lead and obsolete items before ordering rather than after.
What a prototype run costs
There is no honest single number, and any supplier who quotes one is either assuming your BOM is trivial or quoting a number that will move. What moves a prototype quote:
- Component cost and quantity — for a small run, the per-unit component cost dominates, because the parts are bought at the same price as a large run but there are fewer of them to spread that price over.
- Line setup — stencil, programming, fixtures and test jigs. This is a fixed cost that a small run carries entirely.
- Board fabrication — and at prototype quantities, the minimum board cost is often higher per unit than a production run.
- Engineering time — the review, the DFM feedback and any design iteration.
The useful way to think about it: a prototype is not a cheap version of the production order. It is a fixed setup cost plus a small number of parts, and it buys you the thing that actually protects the production budget — knowledge about whether the design works.
Designing a prototype that survives volume
The prototype that pays for itself is the one that finds problems while they are still cheap to fix.
- Run a design-for-manufacturability review before you commit. Part spacing, polarity, panelization, test point access and thermal load are all checkable on a drawing.
- Test the things that will actually fail. A working sample that nobody has stress-tested tells you the design powers on, which is the easy part.
- Build to the real design, not a simplified version. A prototype that differs from production in any way that matters is a prototype of a different product.
- Plan the iteration. The first build is meant to produce information. Budget for a second one, and say so at the quote stage rather than treating it as a surprise.
When a prototype is the right spend
When the design is new enough that you do not yet know whether it can be built, when the part count is high enough that a placement error is expensive, when you need working units to test a market, or when the design carries anything that will be hard to change later — the enclosure, the moulded part, the firmware architecture.
When it is not: when the design has already been built before, and you are simply scaling a known-good board. Then the first production run is the prototype, and it should be planned as one.
Send the Gerbers, the BOM and the assembly drawings and we will tell you which of these you are looking at.